Red Iron Delivered
Workers had to deal with heavy rain but they did get eleven (11) semi-trailer loads of steel unloaded today. The Steel is the super-structure for the first phase of the buiding. The contractors had expected to be ready to erect the steel about the time it was delivered but rain delays have slowed the process. Since the ground is supersaturated with moisture, it is expected that very little work can be done next week.