It is our desire at Melbourne School District to keep the communities informed about the progress on the construction of the new high school facility. We will post updated information and pictures from time to time to allow everyone to share in the progress of the facility. We truly hope you find the site informative and useful. Please feel free to contact us by email at geraldc@katz.ncsc.k12.ar.us if you have questions or other information you would like to see added to this site.

Friday, October 27, 2006

Red Iron Delivered

Workers had to deal with heavy rain but they did get eleven (11) semi-trailer loads of steel unloaded today. The Steel is the super-structure for the first phase of the buiding. The contractors had expected to be ready to erect the steel about the time it was delivered but rain delays have slowed the process. Since the ground is supersaturated with moisture, it is expected that very little work can be done next week.

Wednesday, October 18, 2006

More Rain Delays

We received four inches of rain on the job site over the weekend and it has delayed the progress on the project. Before the rain started, all the walls on the lower level had been poured and the forms removed. The only progress this week has been by Brown Construction. They have been tieing the steel to put in the footers of the main building. In addtion, the contractor has been pumping surface water from the site to facilitate the drying process and allow the workers to continue the process. It is expected the work will continue as planned Thursday afternoon.

Thursday, October 12, 2006

Pictures of Progress





The pictures are of the walls on the lower level and the asphalt on the parking lot.

Friday, October 06, 2006

Wall Poured

The footings and the half the walls on the lower level have been completed. It is expected the asphalt will be started on the parking lot on Monday. The weather has been very cooperative the past few weeks and the progress has been faster than expected. We have received $373,000 from the state facilities division as reimbursement at this point and have turned in documentation to receive another $475,000 for the past quarter of the year.