It is our desire at Melbourne School District to keep the communities informed about the progress on the construction of the new high school facility. We will post updated information and pictures from time to time to allow everyone to share in the progress of the facility. We truly hope you find the site informative and useful. Please feel free to contact us by email at geraldc@katz.ncsc.k12.ar.us if you have questions or other information you would like to see added to this site.

Friday, January 26, 2007

Math/Science/Classrooms/Gym


The weather has cooperated this week and the contractors have made good progress. They have about half the red iron installed on the math/science section and they are working on the footing on the other half. Also they are pouring the footing in the next classroom section and preparing the drains under the gym floor. The picture shows the agriculture building on the left, the regular classroom section in the middle and half of the math/science section on the right.

Tuesday, January 16, 2007

Cold Weather

The cold weather has temporarily stopped progress on the project. The sub-contractors have not been able to pour the footers or install the blocks on the walls. They will not be able to continue until the weather warms to near 45 degrees. It is expected that work can begin next week.

Friday, January 12, 2007

Interior Walls



The block layers have been on the site installing the interior walls in one of the classroom sections. Also, the sub-contractors have continued to install the red iron on the agriculture and classroom sections. The pictures show the red iron and the interior block walls along with the hopper used to mix the mortar for the blocks.

Thursday, January 04, 2007

Agriculture Building


Work continues on the red iron installation of the classroom section of the building and also the agriculture building. The masonry contractors are expected to begin laying blocks as early as Monday. Pictures are of the classroom section red iron and the building closer to the camera with a different roof alignment is the agriculture building. You can click on the pictures to enlarge them.