Melbourne School District
It is our desire at Melbourne School District to keep the communities informed about the progress on the construction of the new high school facility. We will post updated information and pictures from time to time to allow everyone to share in the progress of the facility. We truly hope you find the site informative and useful. Please feel free to contact us by email at geraldc@katz.ncsc.k12.ar.us if you have questions or other information you would like to see added to this site.
Monday, April 30, 2007
The contractors have only two more columns to install on the gymnasium. They have installed the cross sections that hold roof metal as they installed the trusses and columns, so they are not very far away from finishing the roof. Also, they are planning on starting the columns on the student union section today. The pictures show the gym and student union areas.
Wednesday, April 25, 2007
Block Layers Continue
The heavy rain last night has temporarily stopped the installation of the red iron but the block layers have continued to work. There were 20 block layers on the site today and according to Mike Caine, project superintendent, they made good progress.
Monday, April 23, 2007
Thursday, April 19, 2007
Wednesday, April 18, 2007
Tuesday, April 17, 2007
Red Iron on Gymnasium
The contractors began yesterday erecting the red iron on the gymnasium part of the building. The picture shows part of the building in the background. The part you see in the background will eventually extend on down and connect to the gymnasium. All of the building will be under one roof and when students arrive in the morning, they won't have to go outside in the heat or cold for classes or lunch. Also, the building has been designed with the latest technology and physical layout to maximize student safety. It has a state of the art security system both internally and externally and computer controlled locks and doors. In additon, it has a built in storm shelter to accomodate all the students and employees.
Wednesday, April 11, 2007
Roof metal and Red Iron
The roof metal has been installed on the math and science section and the installation of the red iron on the gym should begin any day. The electricians and plumbers are on the job every day and have made some great progress. If the weather holds, the contractors will pour the slab on the student union section in a few days.
Monday, April 09, 2007
Student Union/Math and Science/Gymnasium
The workers have almost completed the roof metal and exterior walls on the math and science section of the building and they are almost ready to pour the slab on the student union. The pictures show the red iron being laid out on the gymnasium, the slab for the student union and the roof metal going up on the math and science section.