Excavation and Water Relocation Progress
The contractor estimates the dirt work will be completed within the next two weeks. Also, the water relocation project is about half complete and is expected to be completed about the same time the dirt work is finished. The contractor on the building construction will be meeting with the other contractors, architect, and superintendent Monday to coordinate the work as it transitions from dirt work to building erection.