It is our desire at Melbourne School District to keep the communities informed about the progress on the construction of the new high school facility. We will post updated information and pictures from time to time to allow everyone to share in the progress of the facility. We truly hope you find the site informative and useful. Please feel free to contact us by email at geraldc@katz.ncsc.k12.ar.us if you have questions or other information you would like to see added to this site.

Wednesday, November 22, 2006

Slab on Business Section

The workers are pouring the slab on the business/technology classroom section today. The plumbers are on the site working in the classroom section in the math and science wing. The weather is cooperating and they have plans to work the remainder of the week. Also, the asphalt crew will continue work on the roads today. They finished the section yesterday on the road that leads out by the Bad Boy/Boeing plant.