It is our desire at Melbourne School District to keep the communities informed about the progress on the construction of the new high school facility. We will post updated information and pictures from time to time to allow everyone to share in the progress of the facility. We truly hope you find the site informative and useful. Please feel free to contact us by email at geraldc@katz.ncsc.k12.ar.us if you have questions or other information you would like to see added to this site.

Tuesday, March 27, 2007

Pictures of Gym Floor Being Poured





Saturday, March 24, 2007

Gym Floor Poured

Brown Construction completed the pour on the gymnasium floor yesterday. They started the process at 4 a.m. and finsished later in the afternoon. There were 300 yards of concrete in the floor not counting the area under the seats or the dressing room/office areas. They are expecting to start with the red iron on the gym this next week. Also, the contractors have installed more roof metal on the science/math area and office areas. I will post pictures of the gym floor as soon as possible.

Tuesday, March 20, 2007

Sheet Panels



The contractors have started installing the side panels above the brick work on the technology section. Also, they have installed more roof panels in the regular classroom section. They have completed the prep work under the slab on the gym floor and will be ready to pour the concrete in the next few days. The pictures show the side panels on the technology section.

Saturday, March 17, 2007

Concrete/Red Iron

Mike Caine with GAG Construction estimates that 50% of the red iron has been installed on the building. Also, approximately 50% of the concrete for the slabs have been poured. The good weather has allowed them to make great progress. They have been laying interior walls and exterior walls and installing the door frames. Also, the sub contractor has made good progress installing the red iron as soon as the slabs have hardened enough for them to get on them. They have the footers poured for the student union area and plan to pour the slab for it in a few days. You may remember, this is the area that has the high vaulted ceiling and this is where the students will stay in and socialize as well as the cafeteria early in the mornings when they first arrive at school.

On the other end of the building, they are preparing the gym floor and dressing rooms floors for the slabs to be poured. They are also finishing the process of installing the french drains around the lower level of the gymnasium.

The contractor discourages people from driving onto the site because of limited space and safety concerns and the strict regulations of OSHA, but if you would like to see the process, contact Mr. Cooper at the school. We are on the site almost every day and would be happy to have you ride along to see the building. Hard hats and safety checks are now required while you are on the building site.

Monday, March 12, 2007

Agri/Technology

The block layers have almost completed the interior walls inside the agri building. It has a large classroom, office, storage, bathrooms, and large shop area. It has 10 welding booths and a dust collection system. They have also been working on the interior walls in the regular classroom section and technology department.

Thursday, March 08, 2007

Aerial View


The aerial view shows the progress the workers have made. You can see the front parking lot is finished except for landscaping around the perimeter and in the islands. The building on the right is the agri building and immediately to the left of it is the technolgy section. You can see the red iron on the office area and one half of the math/science section toward the back. The gymnasium is the large building at the top left of the picture. All these sections and the cafeteria will be connected when the building is completed. The road at the top left is the entrance from the airport road. The other entrance is not visible but it is in the lower right section of the picture. You can double click the picture to enlarge it.

Science/Gym/Storm Shelter



John Brown Construction has poured the second half of the science department slab and they have finished pouring the slab under the seating areas of the gymnasium. The first picture shows the workers finishing the slab under the storm shelter area and the second picture shows the slab on the second half of the science section.

Monday, March 05, 2007

Agri/Technology/Science



The contractors have made the following progress: 1. Erected red iron on office area 2. Poured footers on student union 3. Layed external blocks on agri and technology sections. 4. Installed drains under gymnasium 5. Prepared the slab area for pouring on the second half of the science section. The pictures show the progress in the technology area and science section.