Cushman Electric has begun work on installing the electrical system that will power the lights in the parking lot. There are 13 lighted islands in the parking lot and the electrical system must be installed before the asphalt is in place. The work on the base for the asphalt is expected to begin on Wednesday and the asphalt for the parking lot and one of the entry roads will be put down shortly after the base is in place. Also, the contractor has been on site preparing for the first initial phase before the concrete work begins on the building.