Progress Again
The workers were on the job until midnight last night finishing up the pour on the classroom section north of the technology department of the building. Work also continues on the slab in the storage area of the gym/PE section on the lower level. They are expecting to begin the erection of the superstructure (red iron) as early as next tuesday on the agriculture section of the building if the weather allows.