Rain Delay
Brown Construction had all the steel in place to pour the concrete Friday on the footings on the lower level. Unfortunately, the 5 plus inches of rain washed dirt into the pour area and they had to take out nearly 15 tons of steel to clean out the footings. They have completed most of the repair and should be ready to pour any day. Also, Edwards Bros. were ready to lay asphalt on the parking lot and roads. The rain put to much moisture in the base so therefore they will have to delay the asphalt until it dries out. It is expected that the area will be ready for asphalt on Monday of next week.